Khulna-Darshana Double Rail Track: Half of project period gone for nothing
প্রকাশিত: ২৩ সেপ্টেম্বর ২০২০, ০০:০০
Two and a half years ago, the government had approved a project to build a double rail line along the existing single track from Khulna to Darshana. The project, aimed at boosting trade activities with neighbouring countries using the Mongla port, was supposed to be implemented from January 2018 till December 2022 at a cost of Tk 3,506.75 crore, of which India will provide 77